Home > Construction > Delay Claims In Construction: A Quick Overview Guide

Delay Claims In Construction: A Quick Overview Guide

Delays are virtually inevitable in the construction industry. Rarely does a construction schedule proceed precisely as planned. Construction delays are so expected that they have their own classifications and terminology.

It is crucial to anticipate delays during building projects rather than be surprised by them. Some hold-ups are critical, whereas others are not material to meeting the contract completion date.

Sometimes, there can be delays by both the employer/property owner and contractor/subcontractors, which can be tricky to level out. 

Delays can be a reason to withhold funds on the final settlement account. A solid understanding of the mechanism of delay claims and taking expert legal advice if necessary is essential for both employers/property owners and contractors.

What is a Delay Claim?

A delay claim is essentially a deduction for damages presented as a counterclaim by the project owner when contractors and subcontractors submit their final accounts for settlement. Alternatively, the contractor or subcontractor may make a claim for loss and expense if they are delayed by another party.

It is possible to legitimately challenge a delay claim in certain situations — such as when no precise completion date is stated in the contract or elsewhere in a written or verbal agreement between the parties.

In the absence of an express completion date, a reasonable time to do the job is implied. A contractor may insist the work was completed in a timely fashion in an effort to resist a delay claim from the employer.

Construction Delay Causes

The cause of construction delays may not be the contractor’s fault. The employer may have requested significant variations to the original project brief or additional works. Both are examples of legitimate and reasonable reasons for completion to be delayed.

As a contractor or subcontractor, it is essential to keep thorough records to evidence why delays have occurred should you need to refute a delay claim later.

Types of Construction Delay

A delay can be classified as critical or non-critical. How the delay is classified depends upon the individual circumstances. 

For example:

  • A critical delay is one that materially affects the completion date
  • The “principle of prevention” means that the contractor cannot be held liable for a completion or instalment delay caused by the other party
  • Concurrent delay is when both employer and contractor are responsible for the delay in completion. Concurrent delays have somewhat of a cancelling out effect. The contractor is entitled to a time extension but not to claim damages

Not all delays are critical to a late completion, and project owners are seldom fooled by contractors claiming delay for events which are not material upon analysis.

Detailed analysis is essential as sometimes main contractors or project owners/employers will claim a reduction for a delay that they themselves have caused.

 What Kind of Delay Analysis is Most Appropriate?

There are two types of delay analysis. One is based on written records (usually easier to resolve), and the other is based on a theoretical approach. 

Analysing who is at fault for a construction delay is a strategic and highly complex process and can itself be the cause of disputes.

Delay analysis can be undertaken: 

  •  Prospectively:  Predicting what impact the delay will have on the project’s progress
  •  Retrospectively: Evaluating the effect the delay has had on the project once the works have been completed
  •  Contemporaneously – Analysing the impact of the delay while it is occurring

The Delay and Disruption Protocol of The Society of Construction Law sets out six methods of delay analysis: 

  • Impacted As-Planned Analysis
  • Time Impact Analysis
  • Time Slice Windows Analysis
  • As-Planned versus As-Built Windows Analysis
  • Retrospective Longest Path Analysis
  • Collapsed As-Built Analysis

Sometimes, contractors want to push on with a theoretical analysis rather than delay further whilst waiting for evidence.  Records could be absent as the event may not have been perceived or identified as something likely to prove controversial later.

This can work in the contractor’s favour if it produces an overestimate of the delay as they suffer no loss. However, if the delay is underestimated, the contractor could still potentially apply for a time extension.

What Must An Employer Do When Filing A Delay Claim?

A delay claim is usually grounds to withhold a percentage of the final settlement. This triggers a requirement for the principal contractor/employer to serve a valid pay less notice which must be completed in the correct format and within the specified time.

Conclusion

To best protect your position, it is vital to seek legal advice when there is a potential for a contested construction delay claim.  Even better, take qualified specialist advice when the contract terms are being drafted.

A professional construction contract will anticipate delays to arise and clarify the procedure behind dispute resolution.Helix Law’s specialist team can offer expert and professional advice in construction delay disputes, particularly in complex scenarios involving delays on both sides.

Posted by:

Jonathan Waters
Solicitor

Request a Call Back

People frequently tell us that we’re approachable and offer great advice.

They also tell us most solicitors are hard to get hold of whereas we’re happy to listen. The reason for this is that we value long term relationships and we’re happy to speak with business people, to invest our time in understanding your business and whatever your concerns are. Only at that point can we understand whether we’re the right people to help you.

Related Blogs: