It is usual for retention to be paid at two different times during the construction process. Often half of the retention will be paid following the completion of the job, often referred to as practical completion. The other half will be paid after the defects liability period ends. This is when employers agree a time to examine a completed job for defects and damages. According to standard contracts, a certificate of making good of defects should be issued if all of the defects raised in the liability period have been dealt with, at that point an employer should make full payment of the second half of the retention.
The initial works contract should specify the due dates for payment and the final payment date for payment of the retention. However the contract you signed might not specify these dates. Section 110 of the Construction Act specifies that these payment dates must be outlined in the contract. If not outlined in the contract, employers are bound by the payment terms set out in the Construction Act and Scheme for Construction Contracts. If nothing is set out in the contract about retention payment dates then the due date is likely to be 30 days after completion or the making of a claim for payment of the retention. The final date for payment where the contract is silent will be 17 days after the due date.
You’ll need to calculate the payment dates in the contract you signed or under the Scheme. Then you can apply for retention release. You should then send the employer or contractor a notice. They are obligated to respond in a limited time-frame if they wish to serve a withholding notice/ notice to pay less – this specifies that the employer or contractor will not pay in full and how the sum withheld and the sum payable is calculated.
If the employer or contractor ignores the application for retention release, you are entitled to receive your retention regardless of their intentions. They must pay first and argue later as they can file a claim against you after paying if they have valid evidence of defects. However, this does not change the fact that you are entitled to recover retention if they do not issue a formal notice.
In short, you’ll need to follow these steps:
- Calculate the contract due dates and final payment dates for the retention payments
- Follow the contract or statutory payment notice procedures
- If you do not receive a notice to pay less, seek legal advice.