Timescales for the final account process vary from contract to contract. It is vital to follow the timescales set out in the contract for final account submission —  otherwise, this can lead to a dispute.

A JCT contract gives a timeframe of two or three months after receipt for the final account to be confirmed.

In contrast, NEC contracts do not specify a final account period but anticipate that this matter will be agreed as the contract progresses.

Each contract will have a different process and timescales. Both parties must be aware of the specific timeframes before work begins. Amendments to a standard contract at the negotiation stage could change the timescales.

Back to previous content
What are the best ways to prevent construction contract retention disputes? Read More
How do we deal with defects within our construction contract final account? Read More
Can any adjustments be made to a construction contract final account? Read More
How do we prepare for a final account in a construction contract? Read More
What is set off/contra charging in the context of a construction contract? Read More